NICET Highway Construction Inspector Level III Practice Exam

Unlock All Questions

Unlock All Questions

Question: 1 / 20

What statement regarding test reports for concrete sidewalks, asphalt pavement, and other constructs is true?

50% required on roadway contracts

Required for federal-aid projects only

Same as roadway contracts

The statement regarding test reports that is true reflects the requirement for concrete sidewalks, asphalt pavement, and other similar constructs to adhere to the same standards and protocols as roadway contracts. This alignment ensures that quality control measures, materials specifications, and testing protocols are consistently applied across various types of construction projects on roadways and other pavement structures.

This similarity in requirements helps maintain the integrity and durability of various paving projects, ensuring that they meet specified performance standards and safety regulations. The consistency also simplifies the oversight and monitoring process for inspectors, as they can apply the same standards and expectations across different types of construction projects.

Regarding the other statements, the notion that reports are only required for federal-aid projects does not encompass all types of contracts, as many local and state-funded projects also require proper testing and documentation. A statement suggesting that 50% is required on roadway contracts might imply a misunderstanding of the percentage needed for compliance; however, quality assurance is often assessed comprehensively, not limited to a specific percentage. Finally, the notion that reports must be submitted in duplicate may not universally apply across all jurisdictions or projects, as submission requirements can vary based on local regulations and the specific nature of the contract.

Submitted in duplicate

Next Question

Report this question

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy